There’s Light at the End of the Tunnel
Work on the asbestos-tainted tunnels is under way and on schedule, OOC General Counsel Pete Eveleth said Wednesday.
Search the Roll Call archive by keyword, date, Congress, section, or tags.
Work on the asbestos-tainted tunnels is under way and on schedule, OOC General Counsel Pete Eveleth said Wednesday.
Any delays in that work has the potential to wreak havoc with the overall schedule.
Critics of the Capitol Visitor Center have long taken aim at Congressional tinkering with an already behind schedule and overbudget project.
In the bill’s report, the AOC is directed to establish a statutory inspector general to audit and report semiannually on management, budget and accounting matters at the agency.
late-2006 joint AOC/GAO “lessons learned” report on the CVC project.
Ungar took the AOC post after the previous project executive stepped down earlier this month, citing health reasons.
Visitor Center’s third project executive in as many months, acting Architect of the Capitol Stephen Ayers looked to the Government Accountability Office to find the man who he hopes will bring the behind-schedule
She will maintain a limited schedule in her District and is requesting respect of her privacy at this time.”
Debbie Wasserman Schultz (D), the newly reformed Appropriations subcommittee on the legislative branch has been asserting its oversight role on the behind-schedule and over-budget Capitol Visitor Center
But the most recent schedule predictions from Gilbane, the AOC’s construction management company, indicate that the earliest a grand opening could take place for the long-awaited facility being built
Wasserman Schultz, the chairwoman of the Appropriations subcommittee on the legislative branch who is leading an aggressive new push for House oversight of the behind-schedule project, said that
[IMGCAP(1)] And although AOC project teams “are continuing to make progress, the contractor continues to miss scheduled activities or ‘milestones,’” Ayers said in prepared testimony before House and
Noting that the AOC is asking for about a 19 percent increase over current funding levels, Rep.
the first operational issues that the Office of the Architect of the Capitol is addressing at the CVC is the development of a Web-based advanced reservation and timed pass system that will be used to schedule
While it is unknown who will oversee the final months of construction (the selection of a new Architect is behind schedule), the early proponents are well-known on Capitol Hill.
Since it appears that Hantman’s successor, who will be appointed by the president and confirmed by the Senate, will not be named for quite a while, AOC Chief Operating Officer Stephen Ayers will
recent evidence that would change our preliminary view that a base project completion date in 2006 will be difficult to achieve and that construction completion in early to mid 2007 is more likely unless AOC
testing the fire protection system, installing interior stone work and commissioning the heating ventilation and air conditioning system, are not likely to be completed in the time period indicated in a schedule
Although AOC officials asserted the stonework could be put back on schedule if it is able to procure larger shipments of stone, GAO questioned whether such a plan would further increase the project
“It looks like you’ll be able to catch up on your schedule but it’s going to cost some extra dollars,” noted Sen. Wayne Allard (R-Colo.), who chairs the subcommittee.