Cost of Keystone XL Pipeline In South Dakota More Than Doubles

Reuters reports that “the cost of the South Dakota portion of TransCanada Corp’s Keystone XL pipeline has more than doubled to $1.974 billion in the last four years the project has awaited federal approval, the company said in a petition filed with the state Public Utilities Commission on Monday.”  

The leap in costs from the previous 2010 estimate of $921.4 million is due to factors including the protracted regulatory process, inflation, currency changes, labour cost increases and materials storage, TransCanada spokesman Shawn Howard said.”  

“The project to build the 1,179 mile (1,900-km) pipeline to carry 830,000 barrels per day of Canadian crude from Alberta’s oil sands to the Gulf Coast, is in its sixth year of waiting for a U.S. permit after running into fierce environmental opposition.”

Recent Stories

Arizona Rep. Andy Biggs weighs governor run and potential clash with Trump pick

Stefanik mostly impresses at Senate Foreign Relations hearing

Experts cautious on designating drug cartels as terrorist groups

States challenge Trump order seeking to end birthright citizenship

Top Democrats continue to oppose Hegseth amid new allegations

Trump’s big bang approach to Day 1