Skip to content

CVC Watch

When the Architect of the Capitol and Government Accountability Office officially said last month that the Capitol Visitor Center would open in November 2008 at a price tag of $621 million, it was the first time in years that the two agencies have agreed on the project’s cost and end date.

Originally, officials had hoped the CVC would run $265 million, but the terrorist attacks of Sept. 11, 2001, created security concerns that brought that price tag up. [IMGCAP(1)]

When construction began at the CVC in 2002, it was expected to open by the 2005 presidential inauguration at a cost of $373 million. Those estimates didn’t last, either. Here, CVC Watch takes a look at what factors brought those figures up, and how the AOC and GAO differed.

June 2003: GAO auditors predict $48 million more needed to complete project, bringing the total to $421 million. The money is appropriated soon after.

November 2004: GAO auditors predict costs to rise $50 million to $100 million because of construction delays and poor management. The AOC still predicts the project will cost $421 million and be complete by summer 2006.

April 2005: Construction delays lead CVC officials to predict a September 2006 opening. Later in the month, Architect of the Capitol Alan Hantman tells appropriators certain portions of the CVC might not open until March 2007, but a fall 2006 opening is still set. Hantman also says a total of $517 million will likely be spent by the time the project is completed.

May 2005: Comptroller General David Walker testifies that the price could rise to $559 million and says a March 2007 opening date is likely. At the same hearing, Hantman maintains a fall 2006 opening is possible, with a price tag of $517 million.

September 2005: Hantman officially says a December 2006 opening is likely. GAO officials predict a summer 2007 opening.

February 2006: AOC officials ask for $20.5 million to cover “operational costs” at the CVC, bringing the price tag to $548 million. They also predict a summer 2007 opening. Later in the month, the AOC predicts construction costs will bring the total to $554 million, while the GAO estimates a $584 million budget.

September 2006: Hantman tells appropriators he expects the CVC to open in September 2007. He also predicts the price could rise past $554 million, but he doesn’t give a specific total. GAO officials are skeptical, saying a December 2007 opening is more likely. The cost could reach $592 million, according to the GAO.

November 2006: The GAO predicts the price of the CVC will rise to $600 million and not open before early 2008. AOC officials say the CVC will open in late 2007.

February 2007: Acting Architect Stephen Ayers predicts a summer 2008 opening for the CVC, with a price of $568 million. The GAO agrees with the opening date but maintains the budget likely will be more than $600 million.

April 2007: Both agencies project a September 2008 opening but still differ on cost.

August 2007: The testing of emergency systems likely will delay the opening until November 2008, the GAO predicts. AOC officials maintain a September 2008 opening is possible.

September 2007: Both agencies agree on a November 2008 opening and $621 million price tag for the CVC.

Recent Stories

Harris warns of ‘massive detention camps’ under Trump

Hammering the ‘first nail,’ lawmakers kick off inauguration construction

House panel helped boost Ohio immigrant pet-eating claims

US seeks damages from ship operator in Baltimore bridge collapse

Members of Congress croon like Frank Sinatra, bust loose like Chuck Brown

Judges wrestle with latest Supreme Court gun rights opinion